01 · Management Credibility

Does management do what it says?

MetGPU Deployment Ramp
85/100

The company reported that additional GPUs were placed into service during the three months ended December 31, 2025, specifically at the Prince George site. (2 met across 2 tracked commitments)

On July 3, 2025, we announced that we entered into a purchase order with respect to approximately 2,400 GPUs for a total purchase price of approximately $130 million, which are to be delivered by the end of calendar year 2025 and installed at our Prince George site.

IREN Limited - Ordinary Shares · QUARTERLY_REPORT · Sep 2025 · p.81
MetMiners Converting to HPC
85/100

The company successfully completed the transition of the Prince George site, displacing all previous Bitcoin mining hashrate to accommodate new GPU infrastructure. (1 met across 1 tracked commitment)

We expect that all of the hashrate capacity at Prince George will be displaced following the full deployment of GPUs at the site.

IREN Limited - Ordinary Shares · QUARTERLY_REPORT · Sep 2025 · p.60

See the full cited Management analysis of IREN Limited - Ordinary Shares

Create free account →
02 · Business Model

How durable is the business?

Large Hosting Contract
80/100

AI Cloud Services revenue grew 130% year-over-year as the company expanded its GPU fleet to approximately 2,100 units. While its share of total revenue dropped to 3.1% due to the massive mining surge, the segment's future trajectory is secured by a massive new $9.7 billion contract with Microsoft. (2 expanding)

Our AI Cloud Services revenue for the three months ended September 30, 2025 and 2024, was $7.3 million and $3.2 million, respectively. This increase was primarily due to an increase in AI Cloud Services customers and contracts.

IREN Limited - Ordinary Shares · QUARTERLY_REPORT · Sep 2025 · p.76

See the full cited Business Model analysis of IREN Limited - Ordinary Shares

Create free account →
04 · Risk

What could break the thesis?

Hashrate and Mining Margin

The risk is easing as the company successfully scaled its hashrate to 50 EH/s, allowing it to increase Bitcoin production to 2,039 BTC (up from 813 BTC) despite network difficulty, significantly boosting revenue. (1 easing, 2 intensifying)

We typically liquidate all the Bitcoin we mine daily and therefore did not have any Bitcoin held on our balance sheet as of September 30, 2025.

IREN Limited - Ordinary Shares · QUARTERLY_REPORT · Sep 2025 · p.58
Contract Quality Over Headline MW

The risk is intensifying as the company formalized a massive $9.7 billion agreement with Microsoft, representing a significant portion of its future revenue and requiring $5.8 billion in dedicated GPU capital expenditure. (1 intensifying, 2 stable)

On November 2, 2025, the Group entered into an agreement with Microsoft Corporation... The total contract value is approximately $9.7 billion over the term of the agreement.

IREN Limited - Ordinary Shares · QUARTERLY_REPORT · Sep 2025 · p.56

See the full cited Risk analysis of IREN Limited - Ordinary Shares

Create free account →